Routine maintenance contracts rarely look like
litigation material. They are usually modest in value, operationally familiar,
and renewed with little thought. Yet the largest housing associations in
England spent £10 billion on repairs and maintenance in the year to 31 March
2025, according to the Regulator of Social Housing, much of it through these
service agreements. When deadlines, notice requirements, and later
correspondence don’t align, an ordinary exit can become a contested claim.
The case study running throughout arose from a real
dispute between a Hertfordshire-based housing association and a specialist
maintenance supplier. The service related to a building that had since been
sold, yet the parties disagreed over whether termination had been validly
effected. The housing association maintained that it had communicated
termination by telephone before the relevant deadline, followed by written
confirmation, while later supplier correspondence appeared to acknowledge that
the relationship was ending.
The financial consequences proved wholly
disproportionate to the simplicity of the original arrangement. The annual
maintenance charge was substantially lower than the eventual County Court
claim, which approached £20,000 once alleged continuing contractual
liabilities, court fees and disputed future charges were added together.
Reaching a complete, documented resolution then required a painstaking review
of correspondence, invoices, credit notes, settlement wording, and procedural
steps, absorbing management time far beyond the service’s value.
For clarity, the matter is described throughout as the
Facilities Maintenance Dispute, which keeps attention on the commercial lessons
rather than the individual organisations. Its value lies in the sequence of
events: notice, acknowledgement, disputed liability, accounting reconciliation,
settlement and discontinuance. Each stage shows how easily operational closure
can separate from contractual, financial, and legal closure when ownership is
unclear, and the supporting evidence doesn’t tell one consistent story.
The central lesson extends well beyond a single
maintenance contract. A service can be commercially finished long before the
contract is contractually, financially, or legally finished, and procurement
must deliberately manage all four dimensions. Research by World Commerce &
Contracting suggests the average business loses almost 9% of value annually
through poor contract management. Renewal controls, written notice, evidence,
invoice treatment, settlement authority and formal closure together determine
whether an organisation genuinely exits a contract.
The Contract Clause
Nobody Notices Until It Matters
Renewal and termination clauses are often treated as
administrative detail until the service is no longer wanted. An automatic
renewal provision can convert an expected expiry into another contractual
period, while a missed notice date can preserve liabilities that operational
teams believed had disappeared. In the Facilities Maintenance Dispute, a
comparatively modest annual arrangement ultimately produced a County Court
claim after the parties disagreed over whether termination had actually taken
effect.
The problem is rarely the absence of a termination
clause; it is whether anyone has translated that clause into an operational
control. Procurement teams should identify the earliest date on which notice
may be served, the final permissible date, the notice period, the authorised
recipient and the permitted method of service. A contract requiring “three
months’ written notice” carries materially different risk from one that simply
ends on its stated expiry date.
Public guidance has moved decisively towards planning
exit from the outset. Good practice guidance on the commercial lifecycle from
the National Audit Office (NAO), published in February 2025, states that plans
for potential routes to end a contract should be built in from the start. The
Cabinet Office Contract Management Playbook, published in March 2026, sets out
eleven policy principles and six key objectives, and encourages a wider
contract register.
Public bodies also face transparency duties once a
contract ends. Under section 80 of the Procurement Act 2023, in force since 24
February 2025, a contracting authority must publish a contract termination
notice within 30 days of a public contract terminating, whether through expiry,
termination, discharge, rescission or court order. Private utilities are
excluded. The broader message is that exit belongs in the lifecycle from award,
rather than being improvised when renewal looms.
Written Notice Means
Written Notice
A telephone call can communicate commercial intention
perfectly clearly while still failing to satisfy a contractual requirement for
written notice. That distinction becomes critical where the contract prescribes
writing, delivery to a named address, service on a particular officer or
another defined procedure. In the Facilities Maintenance Dispute, an asserted
pre-deadline telephone termination became central because written confirmation
followed later, raising the question of whether commercial communication and
contractual notice could be treated as equivalent.
English contract law generally respects the
formalities parties choose. In Rock Advertising v MWB Business Exchange Centres
(2018), the Supreme Court upheld a clause requiring variations to be in writing
and signed, so an alleged oral agreement to reschedule licence fee arrears was
ineffective. The case concerned variation, not termination, but the lesson
travels: where parties specify how rights must be exercised, informal
conversations cannot be assumed to achieve the same result.
Method of service matters as much as content. In
Greenclose v National Westminster Bank (2014), the bank needed to serve notice
extending an interest rate collar by 11 am on 30 December. The customer’s fax
machine was switched off for the holidays, so the bank left voicemails and sent
emails. The High Court held that email was not a permitted method under the
agreement, so the notice was ineffective and the extension failed.
That does not mean every imperfect notice is
automatically ineffective. In Mannai Investment v Eagle Star (1997), the House
of Lords upheld break notices stating the wrong date because a reasonable
recipient would have understood the intention. Lord Hoffmann nonetheless
observed that if a clause required notice on blue paper, pink paper would not
do. Outcomes therefore depend on the contractual wording, the defect itself,
the recipient’s understanding and applicable legal principles.
Procurement should therefore avoid turning a practical
rule into an absolute legal proposition, while still adopting a strict
operational standard. The safer approach is simple: comply exactly with the
notice clause, use a prescribed method that produces proof of delivery, retain
evidence of dispatch and receipt, and obtain legal advice promptly where a
deadline, address or method is disputed. Exact compliance removes arguments;
partial compliance merely invites the other party to test them.
The distinction protects suppliers too. A supplier
facing termination needs certainty about whether to keep allocating engineers,
holding stock, maintaining insurance or reserving specialist capacity. Informal
remarks such as “we will not need the service next year” may shape expectations
without ending anything. Procurement professionals should resist treating “the
supplier knew we were leaving” as a substitute for evidence: a signed notice,
the clause relied upon, proof of authority, a delivery record and any
acknowledgement.
The Difference
Between Commercial Intent and Contractual Compliance
Commercial reality and contractual reality can
separate surprisingly quickly. Operational managers may stop using a service,
Finance may remove future budgets, and both parties may discuss final invoices.
Yet, the agreement can remain legally alive if its termination machinery has
not been satisfied. A contract can end operationally long before it ends
contractually, financially, or legally, leaving several separate closure
processes running at once, often without anyone noticing they have diverged.
URE Energy v Notting Hill Genesis shows how much can
turn on that gap. URE supplied electricity to Notting Hill Genesis, one of
London’s largest housing associations, under a four-year contract. On 31
October 2018, URE purported to terminate for an alleged breach concerning meter
access, but then revoked that notice after concluding that it first had to allow
the customer to remedy. It later relied on a different contractual right.
That second notice, served on 5 November 2018, relied
on clause 10.2(d), which permitted termination where the customer passed a
resolution for winding up, defined to include amalgamation. Genesis Housing
Association and Notting Hill Housing had amalgamated in April 2018. The
Commercial Court upheld the termination in 2024, accepting URE’s construction
of the payment clause, under which it claimed £3,946,861.56. The Court of
Appeal dismissed the customer’s appeal in November 2025.
The decision turned on particular wording and facts,
so procurement teams should not generalise the outcome. The underlying warning
is clearer: perceived commercial finality does not override the contract’s
agreed allocation of rights and remedies. Teams should test every exit against
four questions. Has the service stopped operationally? Has the contract ended
under its own terms? Have invoices, credits and commitments been reconciled
financially? Has any claim or court process been concluded legally?
Why Contract Exit
Needs an Owner
Contract exit needs a named owner because deadlines do
not manage themselves. Procurement may maintain the central register, but
responsibility often sits across contract managers, budget holders, operational
teams, Finance, Legal and senior approvers. Without a single accountable
person, each participant may reasonably assume that somebody else has diarised
the notice date. The failure rarely appears dramatic at first; it surfaces only
when renewal occurs, or termination is challenged.
Government contract management guidance explicitly
calls for clear ownership, defined roles, and a documented contract management
plan, and asks whether a responsibility matrix shows who is accountable for
each key activity. Those principles matter just as much in private
organisations. Ownership should establish who monitors expiry, who decides
whether the requirement continues, who obtains approval, who signs the notice,
and who verifies the right person has received it.
The control begins with a reliable contract register that
records the commencement date, expiry date, extension options, automatic
renewal provisions, notice period, and notice method. Alerts should arrive
early enough to support a genuine commercial decision, not merely to allow time
to post a letter. For significant arrangements, a structured review around 180
days before expiry gives the organisation room to decide, approve and act
without being driven by the calendar.
At that review, the owner should test continuing need,
supplier performance, budget, market conditions, procurement lead time and
transition requirements. An organisation deciding to retender may need months
for specification, competition, evaluation, governance approval, and
mobilisation, and public bodies must usually allow a mandatory
eight-working-day standstill period after an award decision under the
Procurement Act 2023. A notice deadline that seems comfortably distant can
quickly become urgent once you map the timetable.
Authority is another frequent weakness. A notice
signed by somebody without delegated authority can create avoidable arguments,
particularly where the contract names authorised representatives. Governance
should establish who may extend, vary or terminate the arrangement and what
internal approval is required. Procurement should preserve the decision record
alongside the notice itself, showing not merely that the organisation
communicated termination, but that it consciously authorised its commercial
consequences before the deadline passed.
Ownership should not end on the final service date.
Under the Procurement Act 2023, most public contracts worth more than £5
million must include at least three key performance indicators (KPIs), and
performance must be assessed at least annually and on termination. The owner
should remain responsible until operational handover, financial reconciliation,
statutory publication and records closure are complete, and the evidence file
can be archived with confidence that nothing remains outstanding.
When Supplier
Conduct Complicates the Picture
Supplier conduct after a disputed termination can make
an already difficult situation more complicated. A supplier may acknowledge the
customer is leaving, discuss final invoices, arrange equipment removal, or
refer internally to a closed account, yet later maintain the contract
technically continued. Those communications can be highly significant evidence,
but procurement should not assume that acknowledgement alone waives every
contractual right or cures every defect in the original notice.
English law distinguishes between contractual rights,
waiver by election, estoppel and ordinary commercial communication. In URE
Energy v Notting Hill Genesis, the Court of Appeal confirmed that a party loses
a right by election only if it knows both the facts giving rise to that right
and the right itself, following Peyman v Lanjani from 1985. URE continued
supplying for around seven months after the amalgamation, yet did not waive its
termination right.
The court acknowledged the tension with commercial
certainty and identified safeguards. Judges should be sceptical of convenient
claims of ignorance; a party that has taken legal advice is presumed to know
its rights unless it proves otherwise, and estoppel may still apply where there
has been an unequivocal representation and detrimental reliance. URE rebutted
that presumption only by waiving privilege over its legal advice, an unusual
and revealing step for any litigant.
In the Facilities Maintenance Dispute, supplier
correspondence acknowledging termination and discussing outstanding invoices
became important because it appeared difficult to reconcile with a later
assertion of continuing liability. It did not automatically determine the legal
position, but it reinforced the need to examine the whole chronology rather
than one isolated clause. Commercial disputes often turn on the interaction of
contractual wording, contemporaneous conduct, correspondence, and the
credibility of competing explanations.
Every material supplier communication after
termination should therefore be preserved and read against the contract.
Procurement should look for acknowledgement of the exit date, requests for
final payment, cessation of service, collection of assets, closure of purchase
orders and references to future obligations. None should be overstated
individually. Taken together, however, they can provide a coherent evidential
picture of what both parties understood, did, and expected immediately after
the purported termination.
The Procurement
Evidence File
Once a disagreement becomes formal, the quality of the
procurement file can matter almost as much as the quality of the original
decision. A chronological evidence pack should include the executed contract,
schedules, variations, purchase orders, invoices, credit notes, emails,
letters, meeting notes, call records, service reports and approvals. The
objective is not volume for its own sake, but the ability to reconstruct who
knew what, when, and what action followed.
Government contract management guidance specifically
recommends storing records centrally so that they remain accessible. This
simple control is critical because disputes often surface long after award and
rarely resolve quickly once issued. Official civil justice statistics show
that, between April and June 2026, the median time from claim to trial in the
County Court was 41.0 weeks for small claims and 55.9 weeks for fast track,
intermediate track and multi-track cases.
By the time a claim reaches a hearing, procurement
staff, operational managers and supplier contacts may all have changed. An
email trapped in a departed employee’s mailbox, or an unsigned contract saved
locally, can seriously weaken an organisation’s ability to establish what
happened. The Facilities Maintenance Dispute turned almost entirely on
sequence: when the call occurred, when written confirmation was sent, when the
supplier acknowledged termination and which invoices then followed.
The file should also distinguish evidence from
recollection. A manager may sincerely remember making a call before the
contractual deadline, but an itemised call record, contemporaneous email or
diary entry will usually be more persuasive than memory reconstructed months
later. Procurement cannot manufacture missing evidence after the event. Its
best defence is disciplined record-keeping at the point of activity, supported
by consistent document naming, version control, central storage and a clear
audit trail.
Do Not Confuse an
Invoice with the Entire Claim
An unpaid invoice is not necessarily the measure of a
contractual dispute. Procurement teams naturally focus on amounts sitting on
the purchase ledger because those values are visible, coded and awaiting
action. A supplier alleging wrongful termination may instead pursue contractual
termination charges, unpaid invoices, interest, costs or common-law damages for
the economic value allegedly lost through premature exit. The ledger balance
can therefore be only one component of a much larger asserted exposure.
The Facilities Maintenance Dispute illustrates the
danger. The disputed annual maintenance charge was substantially below the
eventual County Court claim, which approached £20,000, so focusing on the
visible invoice would have understated the problem. Once a claim is issued,
procurement should reconcile each element separately: invoiced debt, Value
Added Tax (VAT), contractual charges, claimed future losses, interest, court
fees, recoverable costs, and any credits the parties have already agreed.
Interest alone can change the arithmetic. Under the
Late Payment of Commercial Debts (Interest) Act 1998, a supplier may claim
statutory interest on a qualifying business debt at 8 percentage points above
the Bank of England reference rate, unless the contract provides a substantial
alternative remedy. The supplier may also claim fixed compensation of £40, £70
or £100 for each debt, depending on whether it is below £1,000, below £10,000
or higher.
Accounting treatment should follow the legal and
commercial character of each amount. Paying an ordinary invoice discharges a
trade debt; paying damages or a negotiated settlement resolves a different
liability. Credit notes may be needed where invoices no longer represent
amounts properly due, while settlement documentation should specify exactly
what the payment releases. Conflating these categories can leave supplier
ledgers inaccurate even after the commercial dispute itself has apparently been
resolved.
A disciplined exposure schedule is invaluable. It
should list each invoice, credit note, contractual charge, damages allegation,
interest calculation, legal fee and settlement proposal, with a status and
evidential basis for each. That prevents double counting and makes negotiation
more rational. Senior management can then compare the realistic downside of
defending the claim with the cost of settlement, rather than deciding based on
a single headline invoice.
Future Contract
Charges and Loss of Bargain
When a customer leaves early, a supplier may argue
that its loss extends well beyond invoices already raised. Depending on the
contract, it may rely on an agreed termination payment or claim damages for
breach. These are different routes. A contractual termination payment arises
because the contract itself defines a payment mechanism. In contrast,
common-law damages compensate for loss caused by breach and remain subject to
causation, remoteness and mitigation.
URE Energy v Notting Hill Genesis falls firmly within
the first category. Clause 10.5 required the customer to pay 50% of the contract’s
remaining value following termination under the relevant provision. The
Commercial Court read “value” as the total amount payable over the remaining
term, rather than the supplier’s net profit, noting that profit is hard to
forecast. The resulting sum was a contractual payment, not a general precedent
on damages.
Common-law damages work differently. Since Robinson v
Harman in 1848, the aim has been to put the innocent party, so far as money
can, in the position it would have occupied had the contract been performed.
Recovery is limited by remoteness under Hadley v Baxendale and by the duty to
mitigate. Procurement should therefore challenge any calculation that
multiplies the annual charge by the remaining years and presents the result as
automatically recoverable.
Termination charges can be challenged, though the bar
is high. In Cavendish Square Holding v Makdessi and ParkingEye v Beavis (2015),
the Supreme Court held that a breach-triggered clause is penal only if it
imposes a detriment out of all proportion to the innocent party’s legitimate
interest. Payments triggered by the lawful exercise of a termination right
generally fall outside that doctrine, so procurement must read such provisions
before serving notice.
When the Commercial
Decision Overtakes the Legal Argument
A contractual defence can be credible yet commercially
unattractive. Once proceedings begin, procurement must weigh the amount claimed
against likely legal spend, management time, evidential uncertainty,
distraction and the probability-weighted outcome. In the Facilities Maintenance
Dispute, a claim approaching £20,000 created the uncomfortable possibility that
defending the principle could consume a substantial share of the sum in dispute
before any judgment was reached at all.
Court fees form part of that calculation. Under the
Civil Proceedings Fees Order 2008, as amended, issuing a money claim above
£10,000 and up to £200,000 costs 5% of the claim value, so a £20,000 claim
attracts a £1,000 issue fee. Hearing fees currently stand at £619 on the fast
track and £1,334 on the intermediate and multi-tracks, before solicitors,
counsel, witnesses or internal management time are considered.
Recoverable legal costs are also more constrained than
many managers assume. For most claims issued on or after 1 October 2023, fixed
recoverable costs (FRC) apply on the fast track, covering claims up to £25,000,
and on the new intermediate track for claims up to £100,000. A winning party
may therefore recover only a fixed sum, leaving any excess legal spend
unrecovered, however convincingly its defence was ultimately vindicated.
The Department for Transport faced a far larger
version of the same calculation in 2019. Eurotunnel challenged the procurement
of no-deal Brexit ferry capacity and claimed about £80 million. The NAO
reported that the department judged it unlikely to defend the challenge
successfully, faced an expedited trial, and set a £35 million negotiating
ceiling. It settled for £33 million, payable in three £11 million instalments,
with legal costs of about £1 million.
The correct comparison is therefore not simply “pay or
fight”. It is expected settlement cost against expected litigation cost,
adjusted for prospects of success and the value of management attention.
Procurement should document that judgement by recording the claim value,
credible defences, external advice, estimated costs, internal resources,
settlement range, and consequences of losing, so settlement appears as a
reasoned value-for-money decision rather than capitulation.
Mediation and the
Courts’ Expectations
Litigants can no longer treat settlement discussions
as an optional courtesy. In Churchill v Merthyr Tydfil County Borough Council,
decided in November 2023, the Court of Appeal held that courts may lawfully
order parties to engage in non-court dispute resolution, provided the order
does not impair the very essence of the right to a fair trial. The Civil
Procedure Rules (CPR) were then amended from 1 October 2024 to make that power
explicit.
The amended CPR adds promoting or using alternative
dispute resolution to the overriding objective and requires courts to consider
ordering or encouraging it when giving directions on fast track, intermediate
track, and multi-track claims. Failing to comply with such an order, or
unreasonably refusing to engage, can now affect costs. For smaller disputes, court-provided
mediation became compulsory for most money claims up to £10,000, effective from
22 May 2024.
For procurement, the practical implication is that
settlement capability should exist before proceedings begin. An organisation
should know who can authorise an offer, what range has been approved and what
evidence supports its position. The Facilities Maintenance Dispute ultimately
ended through negotiated settlement, delivering what the courts now actively
promote: lower cost, faster closure, and terms, such as agreed credit notes,
that no judgment could have provided.
Settlement Is Not an
Admission of Liability
Commercial settlement exists because litigation risk
is rarely binary. Parties can fundamentally disagree about liability yet agree
that certainty is worth more than another year of correspondence, legal costs,
and management distraction. In the Facilities Maintenance Dispute, settlement
could therefore be justified without accepting that the disputed termination
was ineffective. Payment can buy finality, release, and procedural closure
without accepting the supplier’s interpretation of the contract.
Settlement wording should make that distinction
explicit. Standard drafting records that payment is made without admission of
liability and in full and final settlement of identified claims. The first
expression preserves the payer’s position on breach; the second defines what is
being extinguished. Neither phrase is decoration. The value of a settlement
lies in knowing precisely which liabilities disappear once the agreed
consideration has been paid and any conditions have been satisfied.
“Full and final” must also be scoped carefully. A
settlement may cover the pleaded County Court claim, contractual liabilities
under a named agreement, interest, legal costs and all claims connected with
specified services. Wider wording can release unknown claims, while narrow
wording may leave peripheral disputes alive. Procurement should align the
release with the commercial objective, ensuring neither historic invoices nor
future allegations accidentally survive outside the agreed settlement
perimeter.
A useful settlement agreement addresses implementation
as well as price. It should identify the payment amount, deadline, and bank
details; the treatment of invoices and credit notes; the VAT position;
confidentiality, where appropriate; costs; discontinuance mechanics; and
confirmation that no further sums are due. Where proceedings already exist,
those procedural steps are essential, because an agreement that resolves the
money but leaves the claim technically alive has not delivered complete
closure.
Settlement should therefore be assessed as a purchased
outcome. The organisation buys certainty over liability, expenditure,
management time, and future claims, which may represent excellent value even
when its legal defence remains respectable. Conversely, a poorly drafted
compromise can pay away money without securing equivalent protection. Properly
structured, settlement is not surrender; it is a controlled exchange of
uncertainty for defined, documented and enforceable finality that both parties
can rely upon.
Without Prejudice
and Subject to Contract
“Without prejudice” and “subject to contract” perform
different functions and should never be merged into a vague formula. In Rush
& Tompkins v Greater London Council (1988), the House of Lords confirmed
that genuine attempts to settle a dispute are generally protected from being
used as admissions on the merits. The policy encourages frank compromise, but
protection depends on the substance and context of a communication, not simply
the heading placed above it.
“Subject to contract” concerns formation rather than
evidence. It ordinarily signals that negotiations will not bind until a formal
agreement is concluded. In Joanne Properties v Moneything Capital (2020), the
Court of Appeal held that exchanges conducted “without prejudice and subject to
contract” did not produce a binding compromise, because the qualification could
be removed only by express agreement or necessary implication. Both labels can
therefore operate together, each serving its own purpose.
Baltimore Wharf v Ballymore Properties, decided by the
Technology and Construction Court in 2026, shows how costly ambiguity can be.
Settlement drafts were headed “subject to contract”; on 24 September 2024, the
claimant’s solicitors confirmed the agreement was “agreed”, and the developer
then signed an execution version without that heading. The claimant never
signed. The court held that the reservation had not been lifted, so no binding
settlement existed, and the litigation continued.
Procurement teams can therefore use the combined
wording during active negotiation when both protections genuinely apply. “Without
prejudice” supports candid compromise discussions, while “subject to contract”
prevents an intermediate email from unexpectedly becoming the settlement
itself. Once the parties intend final terms to bind, they must be equally
clear, documenting authority, agreed terms and the exact moment of commitment,
because lingering conditional language can create a second dispute about
whether settlement ever occurred.
Never Pay Before the
Settlement Terms Are Clear
Payment should follow a concluded settlement, not
serve as the way to discover whether one exists. Before funds move, procurement
should have a written agreement on the settlement sum, payment deadline,
release, costs, interest, VAT treatment and disposal of any proceedings. Where
invoices are to be cancelled or credited, identify those accounting steps in
advance, so payment cannot later be characterised as satisfying a different
liability.
Scope is particularly important. An illustrative
£19,000 settlement may appear clear until one party later argues that accrued
interest, court fees, another invoice or a future contractual charge falls
outside it. The agreement should state whether the figure is inclusive or
exclusive of each relevant component and whether it extinguishes all claims
arising from the identified contract. Ambiguity at this stage converts one
dispute into a second dispute about the settlement.
VAT requires specific attention because labels do not
determine tax treatment. His Majesty’s Revenue and Customs (HMRC) confirmed in
Revenue and Customs Brief 2 (2022), applying from 1 April 2022, that most early
termination fees are further consideration for the original supply and
therefore follow its VAT liability, even when described as compensation. By
contrast, genuine damages payments with no supply in return can fall outside
the scope of VAT.
The settlement document should therefore reflect the
actual transaction, rather than assume that every payment is automatically
taxable or automatically outside VAT. HMRC’s earlier Brief 12 (2020), which
took a broader view, was suspended in January 2021 and later replaced,
illustrating how unsettled the boundary can be. Where termination charges,
damages and previously invoiced taxable services are mixed, Finance and tax
advisers should confirm the treatment before signature.
Where proceedings are underway, the parties should
agree the court-closing mechanism before payment. The claimant might undertake
to file and serve a notice of discontinuance, ordinarily on Form N279, within a
set number of days of cleared funds, and to provide a copy to the defendant.
The payer should know exactly what evidence will demonstrate completion. “We
will withdraw the claim” is far less useful than a defined obligation.
The settlement should also specify what happens if
either party fails to perform, including late payment, the continued validity
of releases, confidentiality and the treatment of existing proceedings. Because
a settlement agreement is itself a contract, legal review is sensible for
material disputes. Only once those points are fixed should payment authority be
released. That sequencing protects both sides: the claimant knows what will be
paid, and the defendant knows what rights are surrendered.
The Forgotten
Accounting Problem – Cancelling the Supplier Invoices
A legal settlement does not automatically repair the
purchase ledger. If supplier invoices remain posted as unpaid while the
settlement is paid separately, Finance can be left with an apparent trade
liability even though the commercial dispute has ended. This creates risks of
duplicate payments, distorted aged-creditor reports, and confused supplier
statements. Procurement therefore needs to connect the legal settlement to the
accounting records, rather than treat them as unrelated administrative
processes.
In the Facilities Maintenance Dispute, invoices
forming part of the disagreement were not to remain payable as ordinary
invoices, so corresponding credit notes were required to reverse them. Each
credit note should clearly identify the original invoice and be processed
through the same supplier account. Otherwise, paying a separate settlement can
leave the original invoice outstanding, prompting automated reminders,
escalation or accidental payment months later by somebody unaware of the
agreement.
Billing control failures can reach a far larger scale.
In December 2013, Serco agreed to repay £68.5 million, excluding VAT, to the
Ministry of Justice after an audit of electronic monitoring billing, and G4S
agreed to repay £108.9 million in March 2014. A Cabinet Office review of 28
major Serco and G4S contracts, worth £5.9 billion, identified seven recurring
weaknesses in financial control, transparency, and transition management.
These distinctions matter for audit. An auditor
reviewing the supplier account should be able to trace the original invoice,
the reason it was disputed, the credit that reversed it and the separate
authority for any settlement payment. That creates a coherent chain between
contractual events and financial records. Marking an invoice “settled” without
the correct accounting document can conceal rather than resolve the ledger
position, particularly where VAT has already been recorded.
A practical control is a settlement reconciliation
schedule that shows every affected invoice, credit note, and separate
settlement amount. Each line should record the document number, gross value,
VAT element, posting status and resulting balance. Procurement, Finance and the
budget owner can then sign off the same picture before payment. After
settlement, the supplier ledger should tell the same story as the signed
commercial agreement, with no unexplained residual balance.
Credit Notes Before
Settlement Payment
The safest sequence is usually to establish the
correct ledger position before settlement money leaves the organisation. If
disputed invoices have already been posted, Finance should process valid
matching credit notes to reverse those trade liabilities. The supplier account
can then be reconciled to confirm which ordinary invoices, if any, remain
legitimately payable. Only after that reconciliation should the separately
authorised settlement payment be released under the agreed terms.
That sequencing reduces the risk of paying twice. If
an organisation pays an illustrative £19,000 to compromise a claim while a
£7,000 disputed invoice remains open, an automated payment run could later pay
the invoice as well. Accounts payable systems are designed to pay approved
liabilities, not to interpret litigation settlements. Correct ledger treatment
removes the liability, rather than relying on someone to remember to ignore it
when preparing the next payment run.
Credit notes must themselves be checked. The value
should correspond with the invoice being reversed, including the correct VAT
amount, and Finance should verify that both documents sit on the same supplier
account. Partial credits require particular care because they may intentionally
leave a residual balance. Procurement should keep the supplier’s credit note
alongside the settlement correspondence, so the reason for each adjustment
remains evident long after personnel change.
Once reconciliation is complete, post the settlement using
the organisation’s appropriate accounting treatment, never against an invoice
that has just been cancelled. Coding depends on the payment’s substance and
internal policy, and Finance may need to distinguish service expenditure, legal
settlement costs, court fees, and recoverable VAT. Procurement’s role is to
give Finance a contractual explanation accurate enough to support that
judgement without later reconstruction.
A Settlement Payment
Is Not an Invoice Payment
An invoice requests payment for a supply, or another
amount asserted to be contractually due. A settlement payment is consideration
given to resolve disputed rights on agreed terms. The two can overlap for VAT
purposes, but they are not synonymous. Where original invoices have been fully
credited, the later settlement should not be described or processed as payment
of those invoices unless the settlement agreement expressly provides for that
treatment.
Tax treatment turns on substance rather than
vocabulary. Calling a payment “damages”, “settlement” or “compensation” does
not decide its VAT treatment; the underlying contractual exchange must be
analysed. A payment that is in reality further consideration for services
supplied will usually carry VAT, while one that compensates for loss without
any supply in return may not. Getting the description right in the agreement
makes the correct tax analysis far easier to support.
Three records must align: the settlement agreement,
the supplier ledger and the payment instruction. If the agreement says invoices
have been cancelled and replaced by an all-inclusive settlement, Finance should
not receive an instruction describing the transfer as payment of those
cancelled invoices. Conversely, if the settlement expressly clears genuine
unpaid invoices, identify that element separately so accounting and VAT
treatment both follow commercial reality.
Clear separation also improves management reporting.
Trade spend, damages, legal settlements and court expenditure answer different
questions about supplier performance and procurement value. Coding everything
as ordinary contract expenditure obscures the true cost of a failed exit and
weakens lessons learned. Financial closure therefore requires more than a zero
bank balance: the accounting records must accurately explain why money changed
hands and on what legal basis.
The distinction matters most when shaping future
contracts. If settlement costs are buried within routine supplier spend,
category managers may underestimate the consequences of weak termination
controls. Recording them transparently lets governance teams identify recurring
causes, quantify leakage, and improve templates and training. Accurate
accounting thus becomes commercial intelligence rather than mere bookkeeping,
turning a painful dispute into evidence that helps prevent the next one.
Closing the Court
Proceedings Properly
Payment does not, by itself, end issued County Court
proceedings. Under CPR 38.3, a claimant wishing to discontinue all or part of a
claim must file a notice of discontinuance and serve a copy on every other
party, ordinarily using Form N279. Procurement should therefore distinguish
carefully between “the money has been paid” and “the proceedings have formally
ended”, because they are separate events that can be weeks apart.
Where permission is not required, CPR 38.5 provides
that discontinuance takes effect on the date the notice is served on the
defendant, not simply when the court receives the form. Subject to the
defendant’s right under CPR 38.4 to apply within 28 days to set the notice
aside, the claim then ends against that defendant, although costs questions may
remain. The defendant should keep the served notice alongside the settlement.
The settlement should allocate responsibility for this
step before releasing funds. Commercial wording commonly requires the claimant,
once payment clears, to file and serve the notice promptly and send evidence to
the defendant. The exact mechanism should fit the proceedings and any legal
advice received. Procurement need not become the litigation manager, but its
settlement checklist should contain a specific legal-closure milestone rather
than ending at payment.
The Facilities Maintenance Dispute makes the
distinction especially clear. Operationally, the maintenance requirement had
ended; financially, the parties could reconcile invoices and credits;
commercially, they could agree and pay a settlement. Legal closure, however,
required a separate procedural act in the County Court. Missing that final step
leaves an avoidable loose end long after everyone involved has assumed, quite
reasonably but wrongly, that the dispute is finished.
Costs After
Discontinuance
Discontinuance should never be assumed to make costs
disappear. Under CPR 38.6, the general rule is that a claimant who discontinues
is liable for the defendant’s costs incurred on or before the date of service
of the notice, unless the court orders otherwise. That general rule does not
apply to claims allocated to the small claims track. Settlement drafting should
therefore address costs expressly, rather than leaving the position to
procedural default.
The small claims exception does not mean that every
party bears its own expenses in every circumstance. Separate small claims costs
rules, with their own limited exceptions, still apply, and a claim may not yet
have been allocated to any track when settlement occurs. A claim approaching
£20,000 would ordinarily be allocated to the fast track, where CPR 38.6 and the
FRC regime both apply.
Procurement professionals should therefore avoid
simplistic assurances in either direction, such as “the claimant always pays
the costs” or “there are no costs in small claims”. Both are misleading. The
settlement agreement can remove that uncertainty by stating exactly how each
side’s legal costs and court fees are treated, including whether the claimant’s
issue fee is absorbed within the settlement sum or remains separately
recoverable.
Commercially, the parties may agree that the
settlement sum includes all interest, fees and costs, or that each side bears
its own legal expenditure. Either approach works if it is clearly expressed.
The aim is to prevent a claimant from receiving the agreed sum and later
asserting an additional entitlement, or a defendant from seeking costs the
claimant believed were settled. The release and costs clauses should always be
read together.
Costs are another reason why commercial resolution can
overtake legal argument. Even a party confident in its interpretation must
consider what it will spend proving that interpretation, what it might recover
under the FRC regime and what internal effort cannot be recovered at all. A
well-drafted settlement converts those uncertain future amounts into a known
figure, and that certainty has an economic value the decision-maker should see.
The Correct Sequence
for Commercial Settlement
Commercial settlement works best as a controlled
sequence rather than a single payment event. In shorthand, the sequence runs:
agreement, authority, credit notes, ledger reconciliation, settlement
confirmation, payment, discontinuance, evidence of court closure and file
closure. The precise order can be adjusted where legal or tax advice requires,
but the control principle remains constant: each stage should create the
precondition for the next, and none should be skipped.
Jumping directly from negotiation to payment weakens
leverage and increases the risk that accounting or procedural obligations
remain unresolved afterwards. The final file should contain the executed
contract, termination correspondence, claim documents, evidence chronology,
settlement authority, binding settlement record, invoices, credit notes,
payment evidence, Form N279 where applicable and confirmation of closure. A
costly dispute should at least leave behind organisational knowledge that
reduces future exposure.
That sequence returns to the central lesson of the
Facilities Maintenance Dispute. Genuine closure arrives only when the
operational, contractual, financial and legal dimensions align and the evidence
proves it. The objective is not merely to stop a service or pay a settlement;
it is to leave no unintended obligation, ledger balance, live proceeding or
evidential gap behind. Lessons learned should then flow back into registers,
alerts and template clauses.
When Contract Exit
Goes Wrong at Scale
The same failures that complicate a modest maintenance
dispute become far more expensive in large public contracts. The Nuclear
Decommissioning Authority awarded a contract worth up to £6.2 billion over 14
years to decommission 12 sites. After the High Court found in July 2016 that
the procurement outcome had been wrongly decided, the authority settled claims
brought by Energy Solutions and Bechtel for £97.3 million in March 2017.
The NAO estimated the episode cost the taxpayer more
than £122 million, including £13.8 million in external advisers and legal fees
and £10.8 million in staff time. The authority also terminated the contract
nine years early, with a 24-month notice period running until 31 August 2019.
Even at that scale, an orderly exit depended on clear notice provisions, a
defined transition period and careful planning for continuity.
Carillion’s liquidation on 15 January 2018 tested exit
planning differently. The company held around 420 public sector contracts, and
the NAO estimated in June 2018 that the collapse would cost taxpayers about
£148 million, excluding pension liabilities. The episode showed why exit plans,
accurate registers and clear information on contractual obligations need to
exist before they are required, rather than being assembled hurriedly under
pressure.
The scale differs, but the controls are recognisably
the same. Teams must understand notice provisions before using them, decisions
must be evidenced, settlements must be authorised against realistic costings,
and transitions must be planned before they are triggered. Whether the contract
is a £6.2 billion decommissioning programme or a single building’s maintenance
service, closure depends on disciplined management of operational, contractual,
financial and legal risk.
The Procurement
Manager as Commercial Coordinator
The procurement manager should coordinate the
commercial response without drifting into the role of litigator. That means
assembling the contract, chronology, supplier correspondence, invoices,
approvals and financial exposure, then ensuring Finance, senior management and
legal advisers work from the same facts. In the Facilities Maintenance Dispute,
procurement could connect commercial context with evidence, leave pleadings,
procedural strategy, and advocacy to qualified advisers, and keep senior
decision-makers informed throughout.
That distinction matters because contract disputes cut
across functions. Finance understands ledger treatment and payment controls;
operational teams know what was delivered; senior management holds settlement
authority; legal advisers assess liability and procedure; procurement
understands the commercial history and supplier relationship. The coordinator’s
task is to integrate those perspectives, identify gaps, and maintain momentum
without presenting personal legal opinion as formal advice.
Government commercial standards support that
collaborative model. Government Functional Standard 008: Commercial (GovS 008)
requires managing supplier relationships according to value, complexity, and
risk, with senior ownership and a defined process for resolving commercial or
legal disputes. Procurement should therefore drive dispute coordination, while
governance determines when technical legal responsibility passes to specialists
and who has authority to approve any resulting settlement.
The scale of public procurement makes disciplined
coordination economically significant. The NAO estimates that £407 billion,
around a third of £1.2 trillion of public sector spending, was spent on goods
and services in 2023-24, with central government accounting for £248 billion.
Its good practice guidance describes a commercial lifecycle that continues
through contract management to exit and transition, rather than ending at
contract award.
Coordination also depends on capability. The Contract
Management Playbook links training accreditation to a contract’s criticality,
complexity and value through bronze, silver and gold tiers, reflecting the
principle that the most significant contracts deserve the most capable
managers. Private sector organisations can borrow the same logic, ensuring that
whoever coordinates a dispute has enough commercial authority, legal literacy
and access to records to keep every function aligned.
What Should Have
Happened at Contract Award
The safest exit starts at award. At mobilisation,
procurement should record the commencement date, expiry date, extension
options, automatic renewal provisions, minimum notice period and prescribed
method of service, and name a contract owner with documented authority and
responsibilities. An organisation that establishes these controls only as
expiry approaches has already surrendered much of the time needed for an
orderly, well-considered commercial decision.
The register should convert legal wording into
actionable dates. If a three-year contract requires twelve months’ notice
before it ends, the register should show the final service date, the latest
valid notice date, and earlier internal decision points, supported by several
reminders rather than a single calendar entry. The objective is not merely to
remember expiry, but to create enough time for evaluation, approval,
competition and transition.
The notice procedure should also be recorded in plain
operational language. A clause requiring written notice, sent to a registered
office by a specified method and deemed received after a defined period, can be
translated into a short instruction for the contract owner. That instruction
does not replace the contract; it makes compliance easier. The executed agreement
and variations should remain available so the instruction can always be
checked.
The Facilities Maintenance Dispute shows the cost of
leaving those controls implicit. Had the notice deadline, authorised sender,
required method and evidence of receipt been captured at award, later
disagreement over a telephone call and subsequent written confirmation would
have been far less likely. Contract registers are therefore not passive
databases; when properly designed, they are control systems that turn
obligations into timely management action before they become disputes.
What Should Happen
180 Days Before Contract Expiry
Six months before expiry is a useful internal control
point for many routine and medium-risk contracts, although complex arrangements
require action much earlier. At 180 days, the contract owner and procurement
should review supplier performance, continuing need, budget, remaining
extension rights, notice requirements and replacement lead time. The decision
should come early enough to preserve every realistic option, rather than
forcing renewal because the work started too late.
Government contract management guidance advises that
planning for exit on larger contracts should begin about 12 to 18 months before
the contract is due to end, with a draft exit plan written at the start of the
contract, or even at award, and reviewed at least annually. For many less
complex arrangements, treat 180 days as a minimum structured decision point
rather than a universal starting date.
Performance evidence should always come first in that
review. The review should assess KPIs, service failures, complaints, pricing,
innovation and relationship quality alongside the organisation’s future
requirements. Renewal should never occur simply because the incumbent is
familiar. Equally, retendering should not be automatic where performance is
strong and a lawful, commercially attractive extension remains available. The
review should decide whether to extend, compete, insource, redesign or
discontinue the requirement altogether.
Public bodies extending or modifying a contract must
also confirm that the change is permitted. Under sections 74 and 75 of the
Procurement Act 2023, modifications must fall within the permitted grounds, and
many require publishing a contract change notice before they take effect. An
extension that seems commercially sensible can still be unlawful if the
original contract did not clearly and unambiguously provide for it from the
outset.
The review must end with authority, not merely
discussion. A named decision-maker should approve the preferred strategy,
procurement should confirm the implementation timetable and the contract owner
should verify the final notice date. If termination is chosen, prepare the
written notice early enough to resolve any questions about authority or method
of service. The 180-day review succeeds only when it produces an owned, dated
and evidenced plan.
Lessons for Supplier
Relationship Management
A dispute does not automatically destroy the supplier
relationship. Mature Supplier Relationship Management (SRM) distinguishes
robust commercial challenge from personal hostility. The Facilities Maintenance
Dispute reached County Court proceedings. Yet the parties could still address
the issues through structured correspondence, reconciliation of invoices and
credit notes, negotiated terms, and an agreed closure mechanism.
Professionalism becomes more important, not less, once both sides have hardened
their positions.
GovS 008 states that supplier relationships should be
collaborative and mutually beneficial, aimed at reducing risk, improving
efficiency and securing value for money, while also requiring a defined process
for handling disputes. Collaboration does not mean avoiding disagreement.
Effective SRM creates channels to escalate, document and resolve disagreements
without unnecessary damage, keeping communication factual even while each party
continues to defend its contractual position vigorously.
Communication quality is often decisive.
Correspondence should separate facts from allegations, identify the contractual
provision in question, state the commercial outcome sought and avoid
inflammatory language. Offers should be clear about status and authority. When
exploring settlement, both sides benefit from knowing what remains disputed and
what has already been agreed, because clear writing stops misunderstandings from
becoming fresh issues layered on top of the original disagreement.
Adversarial procedure and professional behaviour are
not opposites. An organisation can defend its contractual position, challenge
invoices and prepare for court while still communicating respectfully and
exploring proportionate settlement. When the economics favour compromise, a
professionally maintained relationship can accelerate resolution and reduce
costs. Even if the parties never trade again, the quality of the exit affects
cost, reputation, management time and the likelihood of secondary disputes.
Ten Controls That
Could Prevent the Same Problem
First, maintain a complete contract register
containing expiry, extension and notice dates. Second, create multiple alerts
well ahead of every contractual deadline. Third, name a contract owner with
explicit accountability for renewal and exit. Together, these controls address
the most common structural weakness: everyone assumes someone else is watching
the calendar. A contract that cannot identify its owner, next decision date and
final notice date already carries avoidable risk.
Fourth, translate each notice clause into a written
operational instruction covering authority, recipient, address and service
method. Fifth, require termination notices to be written, approved and
evidenced. Sixth, obtain and retain acknowledgement of receipt wherever
possible. These controls will not eliminate every legal argument, but they
dramatically improve the evidential position by replacing recollection and
informal conversation with contemporaneous documents that can be produced
immediately if challenged.
Seventh, maintain a central evidence file containing
the executed contract, variations, emails, call records, invoices, credit notes
and approvals. Eighth, reconcile disputed invoices and process any credit notes
before making settlement payments. These two controls connect the commercial
story to the financial one, ensuring that the documents explaining why a
contract ended also explain why money did, or did not, change hands afterwards
between the parties.
Ninth, establish a formal escalation route that
identifies when Finance, senior management, and legal advisers become involved,
and who may authorise settlement within what range. Early escalation preserves
options, including negotiation and mediation, that the courts now actively
expect parties to consider. Late escalation tends to arrive after positions
have hardened, evidence has dispersed and court fees, legal costs and
management time have already begun to accumulate.
Tenth, require formal closure across all four
dimensions: operational, contractual, financial and legal. Confirm service
cessation, conclude contractual rights, reconcile supplier accounts and
formally end any proceedings. The final file should record lessons learned and
feed them back into templates, registers and training. The strongest control is
therefore circular, because every difficult exit should improve the
organisation’s ability to manage the next contract before another dispute
develops.
Summary – Contract
Exit Is Part of Contract Management
Procurement discipline does not end when a competition
closes, or a contract is signed. The NAO describes a commercial lifecycle
extending from identifying need through procurement and contract management to
exit and transition. Across a public procurement estate worth hundreds of
billions of pounds each year, and an even larger private sector supply base,
the quality of exit management affects a vast volume of spending and commercial
performance.
The Facilities Maintenance Dispute shows how quickly a
routine exit can become disproportionate. A service regarded operationally as
finished became a County Court claim approaching £20,000 because notice,
contractual interpretation, supplier expectations, invoices and procedure did
not align. The lesson is not that every disputed termination ends in
litigation, but that weak closure controls can amplify a modest contract into a
much larger financial and management problem.
The case law points the same way. Rock Advertising and
Greenclose show that agreed formalities matter; URE Energy v Notting Hill
Genesis shows that a contractual termination payment can dwarf annual charges;
Baltimore Wharf shows that settlement itself needs disciplined documentation;
and the Eurotunnel and Magnox settlements show that commercial judgement often
decides outcomes. Each confirms that a contract can be commercially finished
long before it is legally finished.
The lasting lesson is prevention rather than
litigation. A well-maintained register, early expiry review, named owner,
correct written notice, reliable evidence file, disciplined invoice control and
defined settlement process cost very little compared with a contested claim.
Effective procurement manages not only how organisations enter contracts, but
how they leave them, and genuine closure arrives only when delivery,
obligations, records and proceedings all tell the same completed story.
Additional articles can be found at Supply Chain Management Made Easy. This site looks at supply chain management issues to assist organisations and people in increasing the quality, efficiency, and effectiveness of their product and service supply to the customers' delight. ©️ Supply Chain Management Made Easy. All rights reserved.
Sources and Further
Reading
- National Audit Office, Good practice guidance: Managing the commercial lifecycle (February 2025) https://www.nao.org.uk/insights/good-practice-guidance-for-managing-the-commercial-lifecycle/
- National Audit Office, Out-of-court settlement with Eurotunnel (2019) https://www.nao.org.uk/wp-content/uploads/2019/05/Out-of-court-settlement-with-Eurotunnel.pdf
- National Audit Office, The Nuclear Decommissioning Authority’s Magnox contract (October 2017) https://www.nao.org.uk/report/the-nuclear-decommissioning-authoritys-magnox-contract/
- Highways Magazine, Carillion collapse to cost taxpayer £148m, says NAO (June 2018) https://www.highwaysmagazine.co.uk/news/archive-news/carillion-collapse-cost-taxpayer-148m-nao
- Procurement Act 2023, sections 78 to 80: Terminating public contracts https://www.legislation.gov.uk/ukpga/2023/54/part/4/crossheading/terminating-public-contracts
- Civil Proceedings Fees Order 2008, Schedule 1 (as amended) https://www.legislation.gov.uk/uksi/2008/1053/schedule/1
- Court and Tribunal Fees (Miscellaneous Amendments) Order 2026 https://www.legislation.gov.uk/uksi/2026/642/made
- Ministry of Justice, Civil Justice Statistics Quarterly: April to June 2026 https://www.gov.uk/government/statistics/civil-justice-statistics-quarterly-april-to-june-2026/civil-justice-statistics-quarterly-april-to-june-2026
- Late Payment of Commercial Debts (Interest) Act 1998 https://www.legislation.gov.uk/ukpga/1998/20
- Regulator of Social Housing, 2025 Global Accounts published (January 2026) https://www.gov.uk/government/news/regulator-of-social-housing-2025-global-accounts-published
- Government Commercial Function, Contract Management Foundation takeaway guide https://www.gov.uk/government/publications/civil-service-helping-you-with-managing-suppliers-and-contracts/contract-management-training-accreditation-foundation-level-takeaway-guide-html
- Government Functional Standard GovS 008: Commercial https://www.gov.uk/government/publications/government-functional-standard-govs-008-commercial-and-commercial-continuous-improvement-assessment-framework/government-functional-standard-govs-008-commercial-html
- DWF, New Contract Management Playbook published by the Cabinet Office (April 2026) https://dwfgroup.com/en/news-and-insights/insights/2026/4/new-contract-management-playbook-published-by-the-cabinet-office
- HM Revenue and Customs, Revenue and Customs Brief 12 (2020): VAT early termination fees and compensation payments https://gov.uk/government/publications/revenue-and-customs-brief-12-2020-vat-early-termination-fees-and-compensation-payments
- Harper Macleod, Replacing Revenue and Customs Brief 12/2020 (summary of Brief 2 (2022)) https://www.harpermacleod.co.uk/insights/replacing-revenue-and-customs-brief-12-2020-vat-early-termination-fees-and-compensation-payments/
- Cabinet Office, Taxpayer compensated for overcharging as cross-government contracts review concludes (December 2013) https://gov.uk/government/news/taxpayer-compensated-for-overcharging-as-cross-government-contracts-review-concludes
- Civil Service World, G4S to repay MoJ £108.9m after overcharging (March 2014) https://civilserviceworld.com/news/article/g4s-to-repay-moj-1089m-after-overcharging
- URE Energy Ltd v Notting Hill Genesis [2024] EWHC 2537 (Comm), CMS summary https://cms.law/en/gbr/legal-updates/energy-the-meaning-of-value-and-waiver-of-termination-rights
- URE Energy Ltd v Notting Hill Genesis [2025] EWCA Civ 1407, Hill Dickinson summary https://www.hilldickinson.com/our-view/articles/court-of-appeal-finds-party-did-not-waive-its-express-contractual-right-to-terminate/
- Greenclose Ltd v National Westminster Bank plc [2014] EWHC 1156 (Ch), Clifford Chance briefing https://cliffordchance.com/content/dam/cliffordchance/briefings/2014/05/giving-notices-high-court-holds-its-a-must-greenclose-ltd-v-national-westminster-bank-plc.pdf
- Baltimore Wharf SLP v Ballymore Properties Ltd [2026] EWHC 312 (TCC) https://caselaw.nationalarchives.gov.uk/ewhc/tcc/2026/312
- Gowling WLG, Civil Procedure Rules embed ADR into the civil justice system (2024) https://gowlingwlg.com/en/insights-resources/articles/2024/civil-procedure-rules-embed-adr-into-the-civil-justice-system
- Addleshaw Goddard, Extension of the fixed recoverable costs regime (2023) https://www.addleshawgoddard.com/en/insights/insights-briefings/2023/dispute-resolution/extension-of-the-fixed-recoverable-costs-regime-what-you-need-to-know/
- World Commerce & Contracting, Contract Management: An Overlooked Driver of Business Agility and Financial Performance (2025) https://info.worldcc.com/contract-management-aug-2025
- Rock Advertising Ltd v MWB Business Exchange Centres Ltd [2018] UKSC 24
- Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd [1997] AC 749
- Joanne Properties Ltd v Moneything Capital Ltd [2020] EWCA Civ 1541
- Rush & Tompkins Ltd v Greater London Council [1989] AC 1280
- Cavendish Square Holding BV v Makdessi; ParkingEye Ltd v Beavis [2015] UKSC 67
- Churchill v Merthyr Tydfil County Borough Council [2023] EWCA Civ 1416